Scrutinising the Brindley Programme: Protecting Taxpayers from Oracle IT Failures
By Cllr Danny Carter · 19 October 2026
Birmingham City Council’s Audit Committee has recently reviewed the progress of the Brindley Programme, a critical IT overhaul that includes the Income Management System (IMS) go-live and the much-delayed Oracle re-implementation. As your Reform UK councillor, I am closely monitoring this project to ensure that the financial mismanagement of the past is not repeated and that Erdington and Pype Hayes taxpayers are protected.
What's happened
The Audit Committee received an update on the Brindley Programme, which oversees the council's financial and HR systems. According to the Audit Committee Report, the new Income Management System has successfully gone live. However, the main Oracle re-implementation has been extended to Summer 2026, with a planned cutover window in July. The programme has undergone independent Stage Gate and Value for Money reviews by Grant Thornton, which highlighted significant risks and ongoing data quality issues that must be addressed before the system can safely launch.
What it means for Erdington and Pype Hayes
While an IT system upgrade might sound like a distant bureaucratic issue, it directly impacts every resident in Erdington and Pype Hayes. The original Oracle implementation failure cost Birmingham taxpayers tens of millions of pounds—money that should have been spent on fixing our roads, cleaning our streets, and supporting local services. If this re-implementation is not managed with absolute precision, we risk further financial black holes that will inevitably lead to higher council tax bills and deeper cuts to the frontline services our community relies on.
Where I stand
I believe that the council must be held to the highest standards of financial accountability. The administration argues that extending the deadline to Summer 2026 is a prudent measure to ensure the system is ready, rather than rushing to meet an arbitrary date. I respect the need to get this right, and I acknowledge the hard work of the officers involved. However, as your Reform UK representative, my priority is ensuring that this delay does not become an excuse for spiralling costs. We cannot afford another blank cheque. I will continue to demand transparency and rigorous oversight at every stage of this process.
What happens next
The Brindley Programme will face its next critical Stage Gate review in April 2026, which will assess the results of User Acceptance Testing and business readiness. Following this, the planned cutover is scheduled for July 2026. My office will be tracking these milestones closely, and I will continue to press the administration for regular, transparent updates to ensure the project remains on track and within budget.
Questions we're asking
As the Reform UK opposition, I am putting these specific questions to the decision-maker on behalf of residents:
- Can Cllr Suleman confirm the exact financial cost to taxpayers of extending the Oracle re-implementation to Summer 2026, as detailed in the January 2026 Audit Committee report?
- What specific, measurable steps have been taken to resolve the "ongoing data quality issues" identified in the Grant Thornton Value for Money review?
- If the April 2026 Stage Gate review reveals that the system is still not ready, what is the contingency plan, and who will bear the financial responsibility for any further delays?
- How is the administration ensuring that the "significant levels of business change" required for this implementation will not disrupt essential council services for residents during the July 2026 cutover?
Have your say
Your voice matters in holding the council to account. Please register on the site to leave a comment below, vote in our ward forum poll, and let me know your thoughts on how we can better protect our community's finances.
Source: Birmingham City Council